Data last collected:
Muscatine · Muscatine · IA
Muscatine Plant #1
Operated by Board of Water Electric & Communications
Published location
Where is Muscatine Plant #1?
This locator uses the coordinates in the approved source record. It shows geographic context, not a site boundary, safety zone or property-risk area.
41.391700, -91.056900
Open the interactive map ↗Map data © OpenStreetMap contributors
Equipment mix
Operating capacity by technology
Grouped from this plant’s represented generator records. Use the IA plant index for regional peers.
See the evidence
Electricity output across the year
Monthly net generation shows the seasonal shape of this plant's represented output. A negative value is retained when the source reports net consumption.
MWh net generation · 2024 final edition · EIA 923 represented operating rows. 12 of 12 supplied rows shown; 0 missing values omitted. Months with no reported numeric value are omitted, not treated as zero.
Read the chart as a table
| Record | MWh net generation |
|---|---|
| 1 | 57,677 |
| 2 | 2,085 |
| 3 | -1,522 |
| 4 | -710 |
| 5 | 55,281 |
| 6 | 67,150 |
| 7 | 75,300 |
| 8 | 78,186 |
| 9 | 72,116 |
| 10 | 12,129 |
| 11 | 60,620 |
| 12 | 73,567 |
2024 monthly net generation
| Month | Net generation |
|---|---|
| 1 | 57,677 MWh |
| 2 | 2,085 MWh |
| 3 | -1,522 MWh |
| 4 | -710 MWh |
| 5 | 55,281 MWh |
| 6 | 67,150 MWh |
| 7 | 75,300 MWh |
| 8 | 78,186 MWh |
| 9 | 72,116 MWh |
| 10 | 12,129 MWh |
| 11 | 60,620 MWh |
| 12 | 73,567 MWh |
Operating generators
| ID | Technology | Fuel | MW | Status |
|---|---|---|---|---|
| 9 | Conventional Steam Coal | SUB | 175.5 | OP |
| 8 | Conventional Steam Coal | SUB | 75 | OP |
| 7 | Conventional Steam Coal | SUB | 25 | OP |
Continue exploring
Similar-capacity plants in the same state
Identity, technology and limitations
Use this record
Questions this evidence can answer
Use the name, place, date and identifiers above to confirm that you have the right Muscatine Plant #1 power plant: capacity and generation | PowerPlantFacts record.
Read the reported values with their units, coverage dates and source notes. Keep observed facts separate from estimates or interpretation.
Follow the primary-source links and check the limitations before using this evidence for a decision, comparison or citation.
A closer look at Muscatine Plant #1
Variation in the published months
Across 10 numeric monthly generation entries, 8 has the highest recorded value (78,186 MWh) and 2 the lowest (2,085 MWh). Their difference is 76,101 MWh. Missing months have not been treated as zero.
Reading the MW column
In the 3 numeric rows displayed in this table, MW ranges from 25 (7) to 175.5 (9). The difference is 150.5 in the column's stated units. This summary covers the displayed rows and retains the table's period and scope.
Generator capacity in different operating conditions
| Generator ID | Technology | Nameplate MW | Summer MW | Winter MW | Minimum load MW |
|---|---|---|---|---|---|
| 7 | Conventional Steam Coal | 25.0 | 20.1 | 20.1 | 6.0 |
| 8 | Conventional Steam Coal | 75.0 | 68.0 | 68.0 | 36.0 |
| 9 | Conventional Steam Coal | 175.5 | 160.8 | 160.8 | 45.0 |
EIA-860 2024 final source. Ratings describe capacity, not actual generation or availability. Missing ratings are not zero.
Source: US Energy Information Administration Form EIA-860 2024 plant and operable-generator workbooks; archive 2024. US EIA-authored information is generally public domain; cite EIA, preserve third-party exceptions, changes and no-endorsement context. Source-specific derived data.