EIA plant 57884

Westlake · Calcasieu · LA

Lake Charles Polymers

Operated by Equistar Chemicals LP

Annual generation193,410 MWhSum of represented EIA-923 rows
Fuel codesNGCodes retained from EIA records
Grid contextMidcontinent Independent Transmission System Operator, Inc..Balancing authority or NERC region

Published location

Where is Lake Charles Polymers?

This locator uses the coordinates in the approved source record. It shows geographic context, not a site boundary, safety zone or property-risk area.

30.196571, -93.321970

Open the interactive map ↗
Capacity is not generation. Nameplate MW describes equipment; annual MWh describes recorded output. Proposed and retired units are not added to operating capacity.

Equipment mix

Operating capacity by technology

TechnologyNatural Gas Internal Combustion Engine16.8 MW represented
TechnologyNatural Gas Fired Combustion Turbine14.3 MW represented

Grouped from this plant’s represented generator records. Use the LA plant index for regional peers.

See the evidence

Electricity output across the year

Monthly net generation shows the seasonal shape of this plant's represented output. A negative value is retained when the source reports net consumption.

118,738
218,717
319,580
412,480
511,142
615,320
718,399
814,213
919,801
1013,667
1118,290
1213,063

MWh net generation · 2024 final edition · EIA 923 represented operating rows. 12 of 12 supplied rows shown; 0 missing values omitted. Months with no reported numeric value are omitted, not treated as zero.

Read the chart as a table
Electricity output across the year — MWh net generation
RecordMWh net generation
118,738
218,717
319,580
412,480
511,142
615,320
718,399
814,213
919,801
1013,667
1118,290
1213,063

2024 monthly net generation

MonthNet generation
118,738 MWh
218,717 MWh
319,580 MWh
412,480 MWh
511,142 MWh
615,320 MWh
718,399 MWh
814,213 MWh
919,801 MWh
1013,667 MWh
1118,290 MWh
1213,063 MWh

Operating generators

IDTechnologyFuelMWStatus
G-900Natural Gas Fired Combustion TurbineNG14.3OP
G-901Natural Gas Internal Combustion EngineNG8.4OP
G-902Natural Gas Internal Combustion EngineNG8.4OP

Continue exploring

Similar-capacity plants in the same state

Identity, technology and limitations
EIA plant ID
57884
Sector
Industrial Non-CHP
Water source
Unavailable
Data edition
2024-final

Use this record

Questions this evidence can answer

01What exactly is this record?

Use the name, place, date and identifiers above to confirm that you have the right Lake Charles Polymers power plant: capacity and generation | PowerPlantFacts record.

02What does the evidence establish?

Read the reported values with their units, coverage dates and source notes. Keep observed facts separate from estimates or interpretation.

03What should I verify next?

Follow the primary-source links and check the limitations before using this evidence for a decision, comparison or citation.

A closer look at Lake Charles Polymers

Variation in the published months

Across 12 numeric monthly generation entries, 9 has the highest recorded value (19,801 MWh) and 5 the lowest (11,142 MWh). Their difference is 8,659 MWh. Missing months have not been treated as zero.

Reading the MW column

In the 3 numeric rows displayed in this table, MW ranges from 8.4 (G-901, G-902) to 14.3 (G-900). The difference is 5.9 in the column's stated units. This summary covers the displayed rows and retains the table's period and scope.

Generator capacity in different operating conditions

Generator IDTechnologyNameplate MWSummer MWWinter MWMinimum load MW
G-900Natural Gas Fired Combustion Turbine14.314.516.03.0
G-901Natural Gas Internal Combustion Engine8.48.08.52.0
G-902Natural Gas Internal Combustion Engine8.48.08.52.0

EIA-860 2024 final source. Ratings describe capacity, not actual generation or availability. Missing ratings are not zero.

Source: US Energy Information Administration Form EIA-860 2024 plant and operable-generator workbooks; archive 2024. US EIA-authored information is generally public domain; cite EIA, preserve third-party exceptions, changes and no-endorsement context. Source-specific derived data.

Power plant research

Before you decide, check these points against the current source.

Things to check