MWPowerPlantFacts

Data last collected:

EIA plant 59003

Two Dot · Wheatland · MT

Two Dot Wind Farm

Operated by NorthWestern Energy (MT wind/thermal)

Annual generation34,841 MWhSum of represented EIA-923 rows
Fuel codesWNDCodes retained from EIA records
Grid contextNorthWestern Energy (NWMT)Balancing authority or NERC region

Published location

Where is Two Dot Wind Farm?

This locator uses the coordinates in the approved source record. It shows geographic context, not a site boundary, safety zone or property-risk area.

46.449444, -110.087222

Open the interactive map ↗
Capacity is not generation. Nameplate MW describes equipment; annual MWh describes recorded output. Proposed and retired units are not added to operating capacity.

Equipment mix

Operating capacity by technology

TechnologyOnshore Wind Turbine9.7 MW represented

Grouped from this plant’s represented generator records. Use the MT plant index for regional peers.

See the evidence

Electricity output across the year

Monthly net generation shows the seasonal shape of this plant's represented output. A negative value is retained when the source reports net consumption.

13,516
23,313
32,442
43,387
53,333
62,347
71,765
81,207
91,857
102,238
114,317
125,119

MWh net generation · 2024 final edition · EIA 923 represented operating rows. 12 of 12 supplied rows shown; 0 missing values omitted. Months with no reported numeric value are omitted, not treated as zero.

Read the chart as a table
Electricity output across the year — MWh net generation
RecordMWh net generation
13,516
23,313
32,442
43,387
53,333
62,347
71,765
81,207
91,857
102,238
114,317
125,119

2024 monthly net generation

MonthNet generation
13,516 MWh
23,313 MWh
32,442 MWh
43,387 MWh
53,333 MWh
62,347 MWh
71,765 MWh
81,207 MWh
91,857 MWh
102,238 MWh
114,317 MWh
125,119 MWh

Operating generators

IDTechnologyFuelMWStatus
1Onshore Wind TurbineWND9.7OP

Continue exploring

Similar-capacity plants in the same state

Identity, technology and limitations
EIA plant ID
59003
Sector
Electric Utility
Water source
Unavailable
Data edition
2024-final

Use this record

Questions this evidence can answer

01What exactly is this record?

Use the name, place, date and identifiers above to confirm that you have the right Two Dot Wind Farm power plant: capacity and generation | PowerPlantFacts record.

02What does the evidence establish?

Read the reported values with their units, coverage dates and source notes. Keep observed facts separate from estimates or interpretation.

03What should I verify next?

Follow the primary-source links and check the limitations before using this evidence for a decision, comparison or citation.

A closer look at Two Dot Wind Farm

Variation in the published months

Across 12 numeric monthly generation entries, 12 has the highest recorded value (5,119 MWh) and 8 the lowest (1,207 MWh). Their difference is 3,912 MWh. Missing months have not been treated as zero.

Generator capacity in different operating conditions

Generator IDTechnologyNameplate MWSummer MWWinter MWMinimum load MW
1Onshore Wind Turbine9.79.79.71.6

EIA-860 2024 final source. Ratings describe capacity, not actual generation or availability. Missing ratings are not zero.

Source: US Energy Information Administration Form EIA-860 2024 plant and operable-generator workbooks; archive 2024. US EIA-authored information is generally public domain; cite EIA, preserve third-party exceptions, changes and no-endorsement context. Source-specific derived data.